The project storyENVIRONMENTAL CONSULTING · GRANART

Environmental regularization of a stone industry.

For Granart, a marble and granite industry in Simões Filho, Intactus prepared the studies and followed the licensing process with the city environmental agency, which ended with the license.

Granart
License completedwith RCE, FGCE, SWMP and PEA studies delivered
01SCOPE AND CONTEXT

Studies and process handled together.

The work covered the classification of the project, environmental studies, a location plan with georeferenced coordinates, maps and the technical responsibility records (ART). Intactus also opened the licensing process and followed its progress with the municipal agency. See our consulting and licensing and PGRS and PEA services.

01 · UNDERSTAND

Characterize the activity

Survey the stone-processing activity and the classification of the project.

02 · STRUCTURE

Prepare the studies

RCE, FGCE, SWMP and PEA (Environmental Emergency Plan), with a georeferenced plan and maps.

03 · FOLLOW UP

Handle the process

Opening of the process, support with supplementary documents and follow-up with the city until the license was completed. The waste plan included registration in SINIR and a waste transport manifest (MTR) for disposal.

02PERSPECTIVE

Complete documentation organizes licensing

An industrial activity calls for connected studies and supporting documents. Intactus organized this set for the municipal environmental agency.